Dependencies and issue lists
When you link tasks and documents with "this must finish first" relationships, Planax automatically determines whether each item can start now, is waiting on a predecessor, or is in progress out of order. These results are used as-is in the filters on the task and document lists and in the issue lists on the project overview.
Create a dependency with a link
In the Links section of a task or document detail panel, you connect other tasks or documents. A link of the blocks type becomes a dependency.
Open the predecessor
Open the detail panel of the task (or document) that must finish first.
Add a link
Click the Add button in the Links section.
Choose a type
Click Select link type... and choose blocks.
Search for the target
In the Search tasks or documents... field, enter the name of the item that should follow.
Select the target
Click an item in the search results. It is linked right away and a "Linked to ..." message appears.
A link always starts from the item you currently have open. If "B can start only after A finishes", open A's detail panel and link B with blocks. In B's Links section, the same relationship appears as is blocked by.
Link types
| Type | Meaning |
|---|---|
| blocks | The linked item can start only after this item finishes (a dependency). |
| clones | Marks this task as a copy made from the linked task. Link tasks to tasks only. |
| duplicates | Marks this task as a duplicate of the linked task. Link tasks to tasks only. |
| relates to | Marks the items as related to each other. |
| references | Marks that this item refers to the linked item. |
| supersedes | Marks this document as replacing the linked document. Link documents to documents only. |
The Select link type... list shows only the types available for the kind of item you have open, a task or a document. Only blocks links count toward dependency status and issue lists. The other types are only for recording relationships.
Check and remove links
- A link card shows the relationship name, the status of the linked item, and its title. Click the title to go to that task or document.
- If there are more than 3 links, click Show more → to see the full list.
- For links you have permission to delete, click the X button (Remove link) on the right of the card.
Dependency status
A successor linked by a blocks link is classified as one of the following, depending on how its predecessors are doing.
| Status | Criteria |
|---|---|
| Ready to start | There are no predecessors, or all predecessors are completed. |
| Waiting on | There is a predecessor that is not finished, and this item has not started yet. |
| Bypass | There is a predecessor that is not finished, but this item is already in progress or completed (an order violation). |
For example, suppose "Gather requirements" is linked to "Draft design mockups" with blocks. Then the status changes as follows.
- If both tasks are To Do, "Draft design mockups" is Waiting on.
- If you change "Draft design mockups" to In Progress before "Gather requirements" is finished, it becomes Bypass.
- If you change "Gather requirements" to Done, "Draft design mockups" becomes Ready to start.
Where it appears
- Status View in the Tasks tab: If the screen is wide enough, each task shows its dependency status, along with the type (task or document) and name of any unfinished predecessor.
- List View: If the screen is wide enough, the names of unfinished predecessors appear next to the title. Cards in Board View show the same information.
- Links section: Each link card shows the current status of the linked item.
Issue filters
The task list and document list have filters based on dependencies and due dates. After choosing a filter, hover over the info icon next to it to see the criteria.
| Filter (Tasks / Documents) | What it shows |
|---|---|
| Due / Due | Items whose due date is within 3 days from today or already past, and that are not yet completed |
| Bypass / Bypass | Items that are in progress or completed even though a predecessor is not finished (the Bypass status) |
For details, see Tasks and Documents.
Issue lists on the project overview
The project Overview shows the dependency status of the whole project at a glance.
| Location | Content |
|---|---|
| Waiting on in the status bar | The number of due-soon items whose predecessors are not yet finished. Click it to go to the task list (Status View) with the Due filter applied. |
| Bypass Issue in the status bar | The number of items in progress ahead of their predecessors. Click it to go to the task list (Status View) with the Bypass filter applied. |
| Wait / Ready Issue List | Collects unfinished items due within 3 days or already past, and splits them into the All, Waiting on (predecessors unfinished), and Ready to start (no predecessors, or all finished) tabs. |
| Bypass Issue List | Shows tasks and documents that are already in progress although their predecessors are not finished, along with the predecessors they jumped ahead of. |
For the widget layout and other widgets, see Project overview.
If some work stays in Waiting on for a long time, first check the assignee and due date of its predecessors. If a Bypass Issue appears, check whether skipping the order was intentional, and finish the predecessors first if needed.