Project overview
Overview is a screen that gathers a project's progress and the work you need to check right now into widgets. Open it by clicking Overview under the project in the sidebar.
The screen has two areas.
- Widget area (left): Shows widgets such as progress, waiting work, work that jumped ahead of its order, and team workload. You can change the widget layout for your own account.
- Info panel (right): Shows the project status, lead, schedule, and tags, along with progress and upcoming schedule.
When you first open it
If you have never saved a widget layout, the No layout has been set dialog opens.
- Use recommended layout: Saves the default widget set as your own layout.
- Arrange manually: Goes straight into edit mode so you can arrange the widgets however you like.
If you close the dialog, you can look around without saving the recommended layout.
Default widgets
These are the main widgets in the recommended layout. Hover over a widget and use the Collapse button that appears to collapse or expand it.
Waiting, Ready to start, and Bypass are determined by the dependencies between tasks and documents. To learn how to set up dependencies, see Dependencies.
Progress / Utilization Bar
Shows the overall state of the project in a single line.
- Progress: The share of work (tasks) that is completed.
- Utilization: The share of unfinished work that can proceed right now.
Click Progress or Utilization on the left to change the measure. The following counts appear on the right, and clicking one takes you to the task list with that condition applied.
| Item | Meaning |
|---|---|
| Active | Number of work items that are in progress |
| Waiting on | Number of work items that are due soon but whose predecessors are not yet finished |
| Bypass Issue | Number of work items in progress ahead of their predecessors |
Wait / Ready Issue List
Collects unfinished work whose due date is within 3 days or already past, and splits it by whether its predecessors are finished.
- All: All unfinished work that is due soon or overdue
- Waiting on: Work that cannot start because its predecessors are not finished
- Ready to start: Work that has no predecessors, or whose predecessors are all finished, so it can start now
Each row shows the name, Dependencies, and Info such as the due date and status. Overdue items get an Overdue badge, and items coming up get a Due soon badge. View Tasks and View Docs at the top take you to the task list or document list with the due soon condition applied.
Bypass Issue List
Collects the tasks and documents that are in progress before their predecessors are finished, that is, work that jumped ahead of its order. It also shows which predecessor was skipped, so use it to check whether the procedure was followed. Use View Tasks and View Docs to open the full list.
Team Workload
Shows each member's workload and load level. Hover over a member to see the load level (Light, Normal, Warning, Critical) and the number of In Progress, To Do, and Overdue tasks. If there are many members, use the left and right arrows to page through them.
Info panel
Click the Expand info panel button at the top right of the screen to open the info panel. Click it again (Collapse info panel) to close it.
Project information
Project Information has two tabs: Info and Description. On the Info tab you can edit the following items directly, and changes are saved immediately.
| Item | Description |
|---|---|
| Status | Choose from Active, On Hold, Completed, Archived |
| Lead | Assign a lead from the project members |
| Start Date, Target Date | The project period |
| Tags | Add tags to categorize the project |
Manage project members in Project settings.
Write a project description
Click the Description tab to show the project About section in the left area. Click Edit, write the project details, reference links, and notes, then click Save. You can use basic Markdown such as headings (#), lists (-), and links ([text](url)).
Progress and upcoming schedule
- Progress: Shows the project progress and its basis (Based on tasks or Based on phases), plus the completed counts for tasks, documents, and phases.
- Phase Progress: If the plan has phases, shows the progress of each phase in order.
- Upcoming Schedule: Shows upcoming events and due dates in date order. Nearby dates appear as Today, Tomorrow, or D-3.
Change the widget layout
The widget layout is a personal setting that applies only to your account. Changing it does not change other members' screens.
Open edit mode
Click the Edit widget layout button (palette icon) next to the info panel button. An Editing layout toolbar appears at the top, and the Widget Library appears on the left.
Add, move, and resize widgets
Drag a widget from the Widget Library onto the canvas, or click + Add widget below the canvas. Drag widgets to move them, and drag the bottom-right corner to resize them. Use the buttons at the top of a widget to swap it for another widget in the same spot, or to remove it.
Save
Click Save in the toolbar to open the Save My Layout dialog. Choose Apply to, then click Save.
The toolbar offers Undo, Redo, Show grid, and Reset to default. To leave without saving, click Cancel.
Save scope and presets
In the Save My Layout dialog, choose the following.
- Start from a preset: Choose one of Default Overview, 3-Column Triage, Risk Focus, or Focus Mode to overwrite the current layout.
- Apply to
- This project only: Applies only to the project you are viewing.
- As the default for all projects I belong to: Applies this layout by default to every project that has no layout saved separately.
You can also manage the default layout for all projects in Account settings.
Widgets with a Demo data badge in the Widget Library (Wait Issue List, Ready Issue List, Overdue Issue List) show sample data, not real project data. To see your actual work, use default widgets such as the Wait / Ready Issue List.